By Arun Kumar Das
RISHIKESH, Oct 11: It was raining here in the hilly region though monsoon was on retreat. Unmindful of heavy rain outside, Anmol and his co-workers were busy laying the tracks inside the 6.1 km long tunnel at Shivpuri in Uttarakhand.
Amid the rains, the track laying work is going on round the clock here as the Rail Vikas Nigam Limited, a PSU of Indian Railways, is gearing up to make a section of the ambitious 125 km long Yog Nagri Rishikesh-Karnprayag rail project operational in 2028.
RVNL is executing the project amid the challenges and difficulties due to the mountainous region and full flowing rivers coming from Himalayan glacier.
PK Gupta, a resident engineer, who was present in the tunnel said track is being laid up to 100 metre a day as the work is going on day and night.
Gupta said some equipment has been imported for the work such as Rail Welding Machine from Holland. But the rails are coming from the Bhilai plant.
The proposed railway line will connect important towns like Devprayag, Srinagar, Rudraprayag, Gauchar and Karnprayag through 5 districts of Dehradun, Tehri Garhwal, Pauri Garhwal, Rudraprayag and Chamoli.
We are expecting to open a 27 km long route from Yog Nagri Rishikesh to Byasi in early 2028 and the work is ongoing round the clock, said Himanshu Bodoni, Chief Project Manager of the national project.
Aiming at providing faster and easy rail connectivity to Chardham pilgrims and tourists in the hilly areas, the entire stretch of 125 km from Yog Nagri Rishikesh to Karnprayag consisting of 16 major tunnels including a 15 km long longest rail tunnel in the country in the country, is expected to be operational in 2029.
Expressing confidence in completing the project in time, Bodoni said the Karnprayag rail link will be an engineering marvel and we are hoping to achieve the target before time.
The tunnels are a major part of the project as the total length of tunnels is 104 km which is 83 per cent of the entire 125 km long rail project.
Besides, there are 12 escape tunnels, 14 maior rail bridges and 12 stations, six road bridges, 38 minor bridges, 5 road over bridges and under bridges.
With the full commissioning of the project, the travel time from Rishikesh to Karnprayag by train will be reduced to 2.5 hours as compared to 6 hours by road.
Currently, the rail connectivity is up to Rishikesh and one has to travel by road for Karnprayag. It takes about 10 to 12 hours for a traveller from Delhi to reach Karnprayag.
According to the Railways, one can reach Karnprayag from Delhi in less than 7 hours by Vande Bharat, once the Rishikesh-Karnprayag rail link is operational, a major boost to tourists and Chardham pilgrimage. At present Vande Bharat service is up to Rishikesh only from Delhi.
Describing the tunnel construction work is a “bit challenging”, Giancarlo Rinaldi, an Italian expert involved in the project, said “Tunnels are being constructed by Tunnel Boring Method and New Austrian Tunneling Method.
“It is a rocky terrain. So rocky materials are changing frequently and then flow of water is also constant from many sources during the excavation,” said Rinaldi.
Railways maintains that the new railway line between Rishikesh and Karnprayag is an important development project in Uttarakhand. The objective of providing rail link to Karnaprayag is for facilitating easy access to pilgrimage centres – Gangotri, Yamontri, Kedarnath and Badrinath – situated in Uttarakhand and to connect new trade centres along with development of backward areas and to serve the population living in the area.
Besides, the line was of strategic importance also for defence needs in the area.
The project was sanctioned in November 2016 with an estimated cost of Rs 16,216.31 cr which has been revised to Rs 37,119.32 cr now.
According to RVNL, there are topographical constraints and challenges. To overcome the constraints of accessibility imposed by rugged topography and to reduce the time frame for the final location survey, state-of-the art surveying techniques based on satellite imagery were used.
The construction of railway lines in rugged Himalayan topography with complex geology is expected to pose risks and technical challenges which demand necessary safeguards at the initial design stage itself to minimize risks and difficulties later during construction and operation stages.
The RVNL had appointed a committee of experts of international repute in the field of railway line construction in hilly areas. The recommendations of the expert committee were duly incorporated in the selection of alignment.
A large number of pilgrims across the country flock to Chardham and a significant number of tourists including foreigners are attracted to trekking and sightseeing in the state. The existing road connectivity travels through fragile mountainous slopes and suffers from serious handicaps of load, capacity, safety and speed.
Railways maintain that with a view to boost up the economy and to develop the backward areas it was decided to connect Chardham and Chardham yatra – Gangotri, Yamunotri, Badrinath and Kedarnath by rail link.
The rail connectivity to these Chardhams will make the travel safer, economical, comfortable, environmentally friendly and all weather.
It is expected that such a link will result in a considerable reduction in travel time and cost. This rail link opens up opportunities for industrial development, cottage industry in the area, boosting the economy and tourism prospects in the state.
The rail route from Rishikesh to Byasi is expected to be operational by early 2028. The remaining 92 km long from Byasi to Karnprayag is expected to be operational by 2029.